Bullet Train TBM Assembly Begins as Cost and Delay Concerns Mount

TRANSPORTATION
Whalesbook Logo
AuthorAarav Shah|Published at:
Bullet Train TBM Assembly Begins as Cost and Delay Concerns Mount
Overview

Assembly of Tunnel Boring Machines for the Mumbai-Ahmedabad High-Speed Rail's 21km underground section has begun. These advanced Herrenknecht TBMs are crucial for digging through complex geology, including residential areas and under Thane Creek. However, the project faces rising costs, now nearing ₹2 lakh crore, and a history of delays. Higher infrastructure input costs from global supply chain issues and the project's geological challenges mean further cost increases and timeline delays are likely, threatening completion dates.

Instant Stock Alerts on WhatsApp

Used by 10,000+ active investors

1

Add Stocks

Select the stocks you want to track in real time.

2

Get Alerts on WhatsApp

Receive instant updates directly to WhatsApp.

  • Quarterly Results
  • Concall Announcements
  • New Orders & Big Deals
  • Capex Announcements
  • Bulk Deals
  • And much more

TBM Assembly Begins for Key Tunnel Section

The assembly of Tunnel Boring Machines (TBMs) has begun for the Mumbai-Ahmedabad High-Speed Rail's most challenging underground section. While the start of work with advanced German machinery signals progress, it also heightens worries about the project's escalating costs and long timeline.

TBM Assembly Underway

National High Speed Rail Corporation Limited (NHSRCL) has started assembling two large Tunnel Boring Machines (TBMs) for the 21-kilometer underground tunnel linking the Bandra Kurla Complex (BKC) and Shilphata. This section is the most technically difficult on the entire 508-km corridor, requiring excavation beneath crowded residential areas and a 7-km stretch under Thane Creek. Assembling each TBM is expected to take at least 97 days.

Rising Costs and Lingering Delays

The project, initially planned for completion in 2023-24, has seen its estimated cost jump 83%, from ₹1.1 lakh crore to nearly ₹1.98 lakh crore. This increase is driven by major delays in acquiring land and higher material expenses. The MAHSR corridor has long faced land acquisition issues, especially in Maharashtra. Worldwide supply chain problems, worsened by events in West Asia, are driving up costs for infrastructure materials like bitumen, steel, and fuel by 15-25%. While advanced TBMs like those from Herrenknecht are necessary for complex geology, their transport and assembly are difficult. Previous delays in TBM deliveries, including machines held in Chinese customs, show how supply chains can affect Indian projects. It's common for large Indian infrastructure projects to face cost overruns exceeding 20% and significant delays due to issues like poor ground studies, contracting methods, and regulatory hurdles.

Persistent Risks: Safety, Debt, and Overruns

The complexity of the Mumbai-Ahmedabad High-Speed Rail's underground section creates a high risk for major cost increases and further delays. TBM assembly is just the first step before difficult excavation begins. Poor studies of ground and soil conditions are a common problem in Indian tunneling projects, leading to delays and cost overruns. The project has reportedly seen safety issues, including a structural collapse in Anand, Gujarat, which killed three workers. NHSRCL and IIT experts are investigating this incident. Critics also question the project's long-term financial health due to its growing debt and high operating expenses. While China has built extensive high-speed rail, its experience also highlights potential debt traps and prioritizing ambition over economic sense, with many routes reportedly losing money. NHSRCL's FY25 revenue was ₹117 crore, against authorized capital of ₹20,000 crore and paid-up capital of ₹15,006 crore, showing a large need for funding.

Revised Timelines and Future Projections

Even with TBM assembly underway, the full 508 km corridor is now expected to open in late 2029. The first section, between Surat and Bilimora, is planned for August 15, 2027. However, the significant engineering challenges, rising costs, and possible unknown geological problems on the BKC-Shilphata section suggest these dates could shift again. The project's success will depend on its ability to manage its estimated ₹2 lakh crore cost and meet the updated schedules.

Get stock alerts instantly on WhatsApp

Quarterly results, bulk deals, concall updates and major announcements delivered in real time.

Disclaimer:This content is for educational and informational purposes only and does not constitute investment, financial, or trading advice, nor a recommendation to buy or sell any securities. Readers should consult a SEBI-registered advisor before making investment decisions, as markets involve risk and past performance does not guarantee future results. The publisher and authors accept no liability for any losses. Some content may be AI-generated and may contain errors; accuracy and completeness are not guaranteed. Views expressed do not reflect the publication’s editorial stance.