Logo
Whalesbook
HomeStocksNewsPremiumAbout UsContact Us

EPC Contract Delays: Are You Losing Millions? Shocking Formulae Revealed by Indian Courts!

Industrial Goods/Services|3rd December 2025, 6:20 AM
Logo
AuthorAditi Singh | Whalesbook News Team

Overview

Disputes in Engineering Procurement and Construction (EPC) contracts often hinge on calculating damages for delays. Contractors claim lost profits and unabsorbed overheads. Indian courts increasingly use formulae like Hudson, Emden, and Eichleay to assess these claims, as recognized by the Supreme Court. However, recent rulings stress that claims must be backed by credible evidence of actual losses, not just formulaic calculations, to avoid rejection.

EPC Contract Delays: Are You Losing Millions? Shocking Formulae Revealed by Indian Courts!

Understanding EPC Contract Disputes

Engineering Procurement and Construction (EPC) contracts are complex, and disputes frequently arise from delays. These delays can be caused by contractors, employers, or external factors, leading to significant financial implications. A central issue in these disputes is determining the 'quantum' of damages, especially when contractors seek compensation for lost profits and unabsorbed head-office or off-site overheads.

Calculating Contractor Damages: Overheads and Lost Profits

  • Off-site/Head-Office Overheads: These are indirect business costs incurred by a contractor that are not tied to a specific project. Examples include administrative expenses, executive salaries, and rent for a central office. When an employer-caused delay extends a project, contractors can claim a portion of these costs for the extended contract period, arguing they cannot easily take on new work or reduce existing overheads.
  • Loss of Profits: Project delays can prevent contractors from undertaking other profitable ventures. Claims for 'loss of opportunity' require demonstrating, often using past financial records and turnover data, the realistic profits that could have been earned during the delay period.

Key Formulae in Indian Jurisprudence

To manage unrealistic damage claims, Indian courts and tribunals often rely on established mathematical formulae. The Supreme Court has recognized the legitimacy of key formulae in cases like McDermott International Inc. v. Burn Standard Co. Ltd.

  • Hudson Formula: This formula is widely used to calculate unabsorbed overheads and lost profit. It's calculated as: (Head Office Overheads and Profit Percentage as in contractor’s tender/100) × (contract sum/contract period) × period of delay. A key constraint is the assumption that the contractor would have recovered these amounts but for the delay, requiring proof of reduced turnover directly attributable to the delay.
  • Emden Formula: Similar to Hudson, but it uses the contractor’s actual head-office overheads and profit percentage. Its application requires strict proof that the owner-caused delay directly prevented the contractor from taking other profitable work or diminished overhead recovery, and that a profitable market existed.
  • Eichleay Formula: Primarily used in US courts, this formula specifically calculates unabsorbed head-office overheads during employer-caused delays. It uses a three-step approach to allocate actual overhead costs based on the delayed project's proportion of total company billings.

The Crucial Need for Evidence of Actual Loss

Recent judicial precedents have emphasized that relying solely on formulae is insufficient. Cases like National Thermal Power Corporation Limited v. Wig Brothers Builders and Engineers Limited and Ahluwalia Contracts (India) Ltd. v. Union of India highlight that claims for damages for overheads and loss of profits may be rejected if the aggrieved party fails to substantiate actual losses.

  • The Bombay High Court in Edifice Developers and Project Engineers Ltd. v. Essar Projects (India) Ltd. upheld an order setting aside an arbitral award where damages were granted without evidence.
  • Similarly, the Bombay High Court in Essar Procurement Services Ltd. v. Paramount Construction noted that awards based solely on formulae without evidence of actual losses suffer from patent illegality and conflict with India's public policy.

What Constitutes Acceptable Proof?

  • Contemporaneous Evidence: Independent, contemporaneous evidence is key. This can include monthly workforce deployment reports, financial statements, and records of tendering opportunities received and declined due to contract prolongation.
  • Loss of Profit Conditions: To establish loss of profit, contractors must prove:
    • There was a delay.
    • The delay was not attributable to the contractor.
    • The claimant is an established contractor.
    • Credible evidence substantiates the claim of lost profitability, such as proof of other available work that was declined due to the delay or a demonstrable drop in turnover directly caused by the delay.

Conclusion

Judicial precedents clearly indicate that claimants must provide credible evidence of actual losses for unabsorbed overheads and lost profits. Arbitral tribunals must examine this evidence. If the evidentiary threshold is not met, courts may set aside awards, emphasizing the practical requirement for documented proof over theoretical calculations in EPC contract dispute resolution.

Impact

  • This clarification of legal principles impacts companies in the construction and EPC sectors, requiring them to maintain robust documentation for claims.
  • Investors in these sectors should be aware that claims for damages will now be more rigorously scrutinized for substantiating evidence, potentially affecting future financial provisions and awards.
  • The ruling promotes greater predictability in dispute resolution, which is beneficial for the sector.
  • Impact Rating: 7/10

Difficult Terms Explained

  • Engineering Procurement and Construction (EPC) Contracts: Contracts where a company is responsible for delivering a project from design through to construction and commissioning.
  • Quantum: The amount or quantity of something; in legal contexts, it refers to the amount of money being claimed as damages.
  • Unabsorbed Overheads: Costs incurred by a contractor's head office or off-site operations that are not recovered because a project is delayed and not generating sufficient revenue to cover them.
  • Jurisprudence: The theory and philosophy of law; also refers to a body of law or legal decisions on a particular subject.
  • Arbitrator: A neutral third party chosen to resolve a dispute outside of court.
  • Patent Illegality: An illegality that is apparent on the face of the record or obvious, often making an award or decision invalid.
  • Public Policy of India: Fundamental principles that underpin the legal system and societal values, which courts uphold to prevent injustice.

No stocks found.


Personal Finance Sector

India's Wealthiest Secret: They're Buying Optionality, Not Just Gold!

India's Wealthiest Secret: They're Buying Optionality, Not Just Gold!


Banking/Finance Sector

Bond Market Frenzy! Top Companies Rush to Raise Record Funds Ahead of RBI MPC Amid Yield Fears!

Bond Market Frenzy! Top Companies Rush to Raise Record Funds Ahead of RBI MPC Amid Yield Fears!

RBI Unleashes Free Banking Boost: Your Savings Account Just Got a Major Upgrade!

RBI Unleashes Free Banking Boost: Your Savings Account Just Got a Major Upgrade!

GET INSTANT STOCK ALERTS ON WHATSAPP FOR YOUR PORTFOLIO STOCKS
applegoogle
applegoogle

More from Industrial Goods/Services

Africa's Mega Refinery Dream: Dangote Seeks Indian Giants for $20 Billion Powerhouse!

Industrial Goods/Services

Africa's Mega Refinery Dream: Dangote Seeks Indian Giants for $20 Billion Powerhouse!

India's Defence Ambition Ignites: ₹3 Trillion Target, Huge Orders & Stocks Set to Soar!

Industrial Goods/Services

India's Defence Ambition Ignites: ₹3 Trillion Target, Huge Orders & Stocks Set to Soar!


Latest News

India's TB War: Stunning 21% Drop! How Tech & Community Are Curing a Nation!

Healthcare/Biotech

India's TB War: Stunning 21% Drop! How Tech & Community Are Curing a Nation!

US Tariffs Hit India Exports Hard! 🚢 Is Finding New Markets the ONLY Hope? Shocking Data & Strategy Shift Revealed!

Economy

US Tariffs Hit India Exports Hard! 🚢 Is Finding New Markets the ONLY Hope? Shocking Data & Strategy Shift Revealed!

Brokers Urge SEBI to Revive Bank Nifty Weekly Options: Will Trading Surge Back?

Economy

Brokers Urge SEBI to Revive Bank Nifty Weekly Options: Will Trading Surge Back?

Byju's Empire in Crisis: Aakash Rights Issue Faces Legal Freeze Amidst QIA's $235M Claim!

Tech

Byju's Empire in Crisis: Aakash Rights Issue Faces Legal Freeze Amidst QIA's $235M Claim!

Shocking Reveal: LIC's ₹48,000 Crore Adani Gambit – Is Your Money Safe?

Insurance

Shocking Reveal: LIC's ₹48,000 Crore Adani Gambit – Is Your Money Safe?

India's Biggest IPO Ever? Jio Platforms Gears Up for Mega Listing - What Investors NEED to Know!

IPO

India's Biggest IPO Ever? Jio Platforms Gears Up for Mega Listing - What Investors NEED to Know!