Monitoring Agency CARE Ratings identifies procedural lapses in Yajur Fibres' IPO fund management, including fund co-mingling and vendor deviations. With ₹31.13 crore still unutilized, both major projects have been delayed to March 2027.

Yajur Fibres IPO Monitoring Report Highlights Governance and Execution Challenges

Total IPO Issue Size: ₹120.408 crore; Total Unutilized Amount: ₹31.13 crore.

Reader Takeaway: Procedural lapses in fund management and project delays to 2027 heighten operational risk for investors.

What just happened

CARE Ratings, acting as the Monitoring Agency for Yajur Fibres Ltd, released its report for the quarter ended September 30, 2026. While the agency confirmed the funds are being used for the stated objects, it flagged significant procedural irregularities regarding financial discipline and project execution.

Why this matters

The report highlights that IPO proceeds were routed through a general cash credit account, causing a co-mingling of funds. Additionally, the company diverted from the vendor list specified in its IPO prospectus for certain capital expenditure. These issues, alongside a project timeline extension to March 31, 2027, raise concerns regarding internal oversight.

Project Status and Delays

Both major capital projects—the shed/capacity addition at Jagannathpur and the greenfield unit at Ujjain—are behind their original schedules. A Board resolution dated May 25, 2026, officially extended the completion deadlines to March 31, 2027.

Risks to watch

Investors should monitor the company's ability to meet the revised March 2027 deadline without further cost overruns. The report notes that the remaining ₹31.13 crore of IPO proceeds is currently parked in fixed deposits with Canara Bank, maturing between January and February 2027. The stock has seen a sharp decline, trading at ₹34.00 compared to its listing price of ₹174.00, reflecting significant erosion in market sentiment.

What to track next

Watch for subsequent quarterly updates from the Monitoring Agency to verify if procedural compliance improves and if the Ujjain and Jagannathpur projects reach completion by the newly set March 2027 deadline.